Infra Update – May 2019

Download (PPTX, 11.1MB)

Completed

  1. Foot over bridge open to public on 9/5/2019
  2. RCC drain and footpath on West Avenue 10 and West Lane 1
  3. Pedestrian crossing and stop line marking
  4. 3M relinquished land for junction widening
  5. E-City plantation drive

Work In Progress

  1. Proposal of increase of the rate of BWSSB water and change of billing cycle.
  2. Commissioning under progress for 11 traffic signals.

Tenders

  • Infrastructure works:
    • RCC Drain & Footpath (West Avenue 2) Velankani Drive – 175 Lakhs
    • RCC Drain & Footpath (West Avenue 4) IFIM Side – 15 Lakhs
    • RCC Drain & Footpath West Avenue 3 (KPTCL Junction to Yokogawa Junction both sides) – 84 Lakhs
    • RCC Drain & Footpath (West Avenue 9) INTERPLEX SIDE – 77 Lakhs
    • Asphalting – West Avenue -10 (Coffee day Jn to Fire Station Jn) – 25 Lakhs
    • Concrete Road – Fire Station Inside roads – 15 Lakhs
    • MS Railing (West Avenue 9) Both Side – 54 Lakhs
    • MS Railing (West Avenue 6) Both Side – 38 Lakhs
  • Electrical works:
    • Smart Lighting – 60 Lakhs
    • The 7 –Way RMU shifting in West Avenue-3 ( Near Timken) – 20 Lakhs
    • Over Head line converting to UG cable in West Avenue-10 ( Canara Bank to Fire station) – 70 Lakhs
    • New Compact RMU to be installed in West Lane-10 ( Near Bank of India) – 9 Lakhs