Author: Rama Subramanian

Infra Update – January 2018

Completed: Road Widening Work at Police Station Entry. Supply & Fixing Shed at SWM Facility. Work In Progress: Foot Over Bridge – Approved by NHAI Construction of Footpath by using the Square pavers including construction...

Infra Update – December 2017

Completed: Providing and laying of Asphalting using 60/70 grade bitumen from Edizi Tools to TCS gate no 3 via Y-Junction, (East Avenue 1& 4). East Phase. Providing and Laying Asphalting 60 70 grade bitumen...

Infra Update – November 2017

Completed: Footpath Work @ West Avenue 9 (NRN Holdings) Footpath Work @ West Avenue 6 (Wipro Junction) Road Widening Work @ West Lane-7 Construction of RCC Culvert East Avenue-4 (Near Continental) Kerbstone Removing &...

Infra Update – September 2017

Completed: Modification of existing street light poles with LED lights, Splitters, Camera, Advertisement Board, etc  at West Phase – 107 Nos Installation of New Street light pole at East Phase – 24 Nos 5...

Infra Update – August 2017

  Completed: Barbide wire Fencing for Trespassers – West Avenue 1 (Near Toll Plaza) Providing MS Railing for pedestrian safety – West Avenue 1 (Near NTTF) Kerbstone Painting along West Avenue 4 & 8....

Infra Update – July 2017

Completed: Footpath & Drain work– West Lane 12 (Arvind Mills Road) Construction of RCC Road at Pump house. Construction of 7KLD STP ESBR Technology at ELCITA office. Providing MS Railing for pedestrian safety near...