Author: Rama Subramanian

Infra Update – April 2018

Completed Construction of RCC drain, relaying pavers and kerbstone along West Avenue 11 (Cyient Road), Electronics City, Bangalore 560100 UPS installation at SBI road, Y Junction and Tech Mahindra Road Modified street light pole...

Infra Update – March 2018

Completed UPS Installation at SBI road, Y junction and Tech  Mahindra road. Supply & Fixing MS Railing Work along West Avenue 6 & 9 Modified Street Light pole Fixing work along West Avenue 9...

Infra Update – February 2018

Completed Asphalting work along West Lane 4 Construction of RCC drain & footpath work at GNAT, West Lane 2 Footpath work along West lane 1 Kerbstone removing & re-fixing – West Lane 2 Kerbstone...

Infra Update – January 2018

Completed: Road Widening Work at Police Station Entry. Supply & Fixing Shed at SWM Facility. Work In Progress: Foot Over Bridge – Approved by NHAI Construction of Footpath by using the Square pavers including construction...

Infra Update – December 2017

Completed: Providing and laying of Asphalting using 60/70 grade bitumen from Edizi Tools to TCS gate no 3 via Y-Junction, (East Avenue 1& 4). East Phase. Providing and Laying Asphalting 60 70 grade bitumen...

Infra Update – November 2017

Completed: Footpath Work @ West Avenue 9 (NRN Holdings) Footpath Work @ West Avenue 6 (Wipro Junction) Road Widening Work @ West Lane-7 Construction of RCC Culvert East Avenue-4 (Near Continental) Kerbstone Removing &...