Author: Rama Subramanian

Infra Update – August 2017

  Completed: Barbide wire Fencing for Trespassers – West Avenue 1 (Near Toll Plaza) Providing MS Railing for pedestrian safety – West Avenue 1 (Near NTTF) Kerbstone Painting along West Avenue 4 & 8....

Infra Update – July 2017

Completed: Footpath & Drain work– West Lane 12 (Arvind Mills Road) Construction of RCC Road at Pump house. Construction of 7KLD STP ESBR Technology at ELCITA office. Providing MS Railing for pedestrian safety near...

Infra Update – June 2017

Completed: Providing MS Railing for pedestrian safety – West Avenue 1 (Infosys Avenue) Construction of RCC Culvert 5th Cross junction – West Avenue 8 Footpath & Drain Works along West Avenue-8 (Police Station Side)...

Infra Update – May 2017

Completed: Footpath & Drain Works along West Avenue-9 (Petrol Bunk Road) 20 e-toilets Installed at various location of Electronics City and Operational– Completed.  (West & East Phase) Construction of 3KL Capacity UG Sump for...

Infra Update – April 2017

Infra Updates – April 2017 Completed: Footpath & Drain Works along West Avenue-9 (Petrol Bunk Road) 20 e-toilets Installed at various location of Electronics City and Operational– Completed.  (West & East Phase) Modification of...

Infra Update – March 2017

Infra Updates – March 2017 Completed: Supply & Fixing Chain Link Fencing for RMU Yard at Siemens – West Avenue 1. (Infosys Avenue) 20 e-toilets Installed at various location of Electronics City and Operational–...